Kinguele Aval HPP

In January 2025, the cofferdam of the second derivation phase of the Kinguélé Aval HPP in Gabon was completed one month ahead of schedule, marking a crucial stage in the construction of the project. Works for filling the main dam have begun.


OTEC Engineering provided commercial, design, and construction consulting services as a consultant for the contractor.