Project of Securing Electricity Power Supply in Libreville, Owendo and Ntoum
Capacity
-
Location
Gabon
Completion date
2010
Work scope:
Construction of BASE SEEG 90/20 kV GIS substation at LIBREVILLE;
Construction of NTOUM 2 225/90 kV distribution substation at NTOUM;
Construction of ANGONDJE 90/20 kV substation at the future Stadium;
Extension of the AMBOWE 90kV substation;
Extension of the OWENDO SEEG 90KV substation;
Extension of the SEEG BELLEVUE station;
Adaptation of the BISSEGUE 90KV substation to the control center and extension of the substation;
A 90 kV overhead line along the railway from the new OWENDO thermal power plant - OWENDO SEEG - NTOUM 2, for an approximate distance of 38 km;
A 90 kV overhead line between NTOUM 2 and ANGONDJE substations over a distance of approximately 50 km;
A 90 kV overhead line between the AMBOWE and ANGONDJE substations over a distance of 15 km;
A 90 kV underground transmission line from the new OWENDO thermal power plant - BISSEGUE - AMBOWE over a distance of 23 km;
A 90 kV underground transmission line between the BASE SEEG and SEEG BELLEVUE substations over a distance of approximately 4 km.
Services:
Feasibility studies
Technical Assistance for contract negotiations.